Affected services:

  • DNS Resolvers
  • RADIUS Servers
  • Verona
  • Altoga
  • Princeton
  • Culleoka
  • Lowry Crossing
  • New Hope
  • CR 494
  • Climax

Network bandwidth upgrade

Scheduled for Thursday 16th April 2020 at 06:00 (Central Time (US & Canada))

Schedule/description of work

We are working with our upstream bandwidth provider to increase our overall bandwidth available to customers. They need to swap out equipment on our end, so this will unfortunately disconnect everyone for 45 minutes to an hour (hopefully less.) After this upgrade speeds will dramatically increase for everyone!

Scheduled start time
April 16, 2020 06:00
Duration
1 hour
Status
Finished

Updates

Upgrade was unable to proceed because the technician had a faulty fiber optic module.

Posted by Graham McIntire